The
expansion project began in 2002 with the purchase of the land for the
new quarry. The overall timeframe to gain the necessary amendments and
approvals for the project is estimated to take two to three years starting
from the
time the planning applications are submitted in October 2005.
We
appreciate that interested parties would like to know when the major
milestones will happen in the planning process. It is hard to predict,
because there are so many aspects to the process of applying for a license.
In the list below, we have indicated approximate timelines for the various
steps involved in gaining approval.
Licensing
Process
1. Georgian initiates community liaison and informal public meetings
(began in December 2002 and ongoing).
2.
Preparation of impact studies and preliminary site plan (completed in
fall 2005).
3.
Analysis and recommendations of impact studies are required for the
completion of the Planning and Land Use Report (also known as the Summary
Statement) and the proposed quarry site plan. These reports document
any mitigation requirements (submitted in October 2005).
4.
Submission of applications to amend the Niagara Escarpment Plan and
Township of Clearview Official Plan (application submitted in May 2005;
technical reports submitted in October 2005).
5.
Review of applications by authorities involved (expected to be 2006-07).
6. Georgian submits an Aggregate Resources Act license application to
the Ministry of Natural Resources (submitted in July 2006).
7.
Formal public meeting for Township Official Plan application (expected
to be late 2006).
8.
Aggregates Resources Act public information meeting is held (October
25, 2006).
9.
Clearview
Township makes decision on Official Plan amendment and makes recommendation
to Niagara Escarpment Commission on its amendment application (possibly
by late 2006/early 2007).
10.Simcoe
County , as the approval authority, approves or denies the township
Official Plan amendment (expected to be early 2007).
11.Niagara
Escarpment Commission holds meeting to review amendment recommendation
from township and the county, and makes decision on the Niagara Escarpment
Plan amendment and on the issuing of a development permit (possibly
by early to mid 2007).
12.
Finalization of Aggregate Resources Act site plans and Ministry of Natural
Resources makes recommendation on license subject to other approvals
noted above (expected to be 2007).
13.
If all applications are approved, applications for a Permit toTake Water
and for a Certificate of Approval for Discharge are made to the Ministry
of the Environment and fill permits may be required from the relevant
conservation authorities (expected to be 2007).
14.
Quarry operations begin once all approvals are in place (expected to
be early 2008).
Impact
Studies
A
key part of the process is determining what impact the new quarry's
operations might have on the property and surrounding area. A variety
of studies are undertaken to identify any impacts and how they could
be mitigated.
The
results of the studies will be reported on at project committee meetings,
at open houses (dates to be determined) and in the Stepping Stones newsletter.
Water
resources - This study includes groundwater studies and the interaction
of groundwater with surface water features (creeks, ponds and springs).
It also documents the location of, and potential impact on, residential
water wells. This study has been completed and recommendations from
the study will be implemented for the life span of the quarry.
Geology
- This study includes testing bedrock for quantity and quality to justify
creation of the quarry. The study is complete, and results indicate
the limestone is both good quality and of sufficient quantity to merit
quarrying operations.
Natural
environment -This study is complete and spanned all seasons. It began
in spring 2003 and continued until the fall of 2005. It includes a thorough
review of all flora, fauna and habitat.
Agricultural
impact analysis -This study is complete and examined the agricultural
capability of the site to determine what farming use might be made of
the land were it not developed as a quarry. It also assessed the impact
of quarrying on adjacent agricultural operations. The investigation
included a soil survey and land use survey to determine any potential
for conflict between the proposed development and any surrounding livestock
operations.
Noise
- This study is complete and focused on the operational noise involved
with the quarry, including noise from trucks, crushers, conveyors and
other activities. The study began in spring 2003 and was completed in
fall 2005. The study assessed the noise impact and made recommendations
as to appropriate locations for extraction and processing.
Blasting
- This study looked at noise and vibration arising from the blasting.
The study assessed the impact of blasting and made recommendations about
the location of extraction and size of the blast. The study was completed
in fall 2005.
Archeology
-This study assessed the site in terms of its archeological potential.
The area's soil is disturbed and testing is done to see if any archeological
artifacts are present. This study was completed in fall 2005.
Cultural
heritage - This study investigated any ‘built heritage resources,’ such
as historically significant buildings. This study is complete
and was submitted in fall 2005.
Traffic
- Completed in 2005, this study looked at traffic counts during the
summer months (peak season for quarry operations). The study also included
an analysis of safety issues, operational issues, road conditions and
site access, and identified the necessary infrastructure needed to accommodate
quarry operations. For instance, Georgian is proposing the creation
of a tunnel under County Road 91 to allow for material from the proposed
new quarry to be easily transported to the processing plant located
in the existing quarry.
Visual
impact analysis - This study began in spring 2003, continued throughout
four seasons, and was completed in fall 2005. Visual impact is assessed
on a 'drive-by' basis, e.g. what someone can see while traveling by
road past the site, as well as what neighbours can see from their specific
properties.
Planning/land
use study (Summary Statement) -This study looked at the overall land
use impact and undertook a policy analysis to determine the appropriateness
of the expansion proposal, taking into account the results of the impact
studies. This study was completed in fall 2005.
These
studies have been completed and each makes recommendations on how potential
impacts of the new quarry can be addressed. These studies are currently
being reviewed by staff at the Township of Clearview , their peer review
consultants, the County of Simcoe , the Niagara Escarpment Commission,
the Ministry of Natural Resources and other commenting community agencies.
|